Article 1169 of the Civil Code: Delay and demand

Status: In force

What does Article 1169 say?

Those obliged to deliver or to do something incur in delay from the time the obligee judicially or extrajudicially demands from them the fulfillment of their obligation.

However, the demand by the creditor shall not be necessary in order that delay may exist: (1) When the obligation or the law expressly so declare; or (2) When from the nature and the circumstances of the obligation it appears that the designation of the time when the thing is to be delivered or the service is to be rendered was a controlling motive for the establishment of the contract; or (3) When demand would be useless, as when the obligor has rendered it beyond his power to perform.

In reciprocal obligations, neither party incurs in delay if the other does not comply or is not ready to comply in a proper manner with what is incumbent upon him. From the moment one of the parties fulfills his obligation, delay by the other begins.

Read the full text on the Supreme Court E-Library

What does it mean in plain language?

Article 1169 of the Civil Code says when a person who must deliver something or do something is legally "in delay": from the time the creditor demands it, in court or out of court. Demand is not needed in three cases: when the law or the obligation says so, when the date was the main reason for the contract, and when demand would be useless. In contracts where both sides owe something, a party is not in delay while the other has not complied.

How does it work in real life?

Joel's unpaid loan

Joel borrowed money from Ana, payable on a set date, with no clause about default. The date passes. Under the first paragraph of Article 1169, Joel is in delay from the time Ana demands payment, for example by a written demand letter.

The wedding cake

Marie orders a cake for her wedding day. The date of delivery is clearly the reason for the contract. Under Article 1169(2), the baker is in delay if the cake is not delivered on that day, even without a demand.

Both sides waiting

Ben agrees to sell his motorcycle to Rico; Rico will pay on delivery. Ben does not deliver, and Rico does not pay. Under the last paragraph of Article 1169, neither is in delay until one of them performs or is ready to perform properly.

What does this mean in practice?

What does Article 1169 say?

Those obliged to deliver or to do something incur in delay from the time the obligee judicially or extrajudicially demands from them the fulfillment of their obligation.

However, the demand by the creditor shall not be necessary in order that delay may exist: (1) When the obligation or the law expressly so declare; or (2) When from the nature and the circumstances of the obligation it appears that the designation of the time when the thing is to be delivered or the service is to be rendered was a controlling motive for the establishment of the contract; or (3) When demand would be useless, as when the obligor has rendered it beyond his power to perform.

In reciprocal obligations, neither party incurs in delay if the other does not comply or is not ready to comply in a proper manner with what is incumbent upon him. From the moment one of the parties fulfills his obligation, delay by the other begins.

Article 1169, Civil Code

Some terms:

  • Obligee or creditor: the person who is owed. Obligor or debtor: the person who owes.
  • Judicial demand: filing a case in court. Extrajudicial demand: a demand made outside court, such as a demand letter.
  • Delay (in Latin, mora): the legal state of being late after demand, which has consequences such as liability for damages.

When is demand not needed?

The three exceptions in the second paragraph:

  1. The obligation or the law expressly says so. For example, a contract that states the debtor is in default without need of demand once the due date passes.
  2. Time was a controlling motive. The date was so important that the contract would not have been made without it, such as a delivery for a fixed event.
  3. Demand would be useless. For example, when the debtor has made performance impossible.

Why does the date of demand matter?

Delay usually marks when interest and damages start. In Verga v. Harbor Star Shipping Services (2024), the Supreme Court moved the start of compensatory interest from the date of judicial demand to the date of the earlier extrajudicial demand, citing Article 1169 and Lara's Gifts v. Midtown. The rates of interest are explained in the legal interest rate.

A written demand has a second effect under a different article. Article 1155 says prescription of actions is interrupted when there is a written extrajudicial demand by the creditor. See how many years to collect a debt.

How do reciprocal obligations work?

In a reciprocal obligation, each party is both creditor and debtor, as in a sale (the seller delivers, the buyer pays). The last paragraph of Article 1169 says neither side is in delay while the other is not complying or not ready to comply properly. Once one side performs, the other side's delay begins. A party who does not comply in a reciprocal obligation may face a demand for fulfillment or rescission under Article 1191.

Which Supreme Court rulings are relevant?

Frequently asked questions

When is a debtor in delay under Article 1169?

From the time the creditor demands fulfillment, either judicially (by filing a case) or extrajudicially (out of court, such as by a demand letter). Article 1169 calls this incurring in delay.

Is a demand letter always required?

No. Article 1169 lists three cases where demand is not necessary: when the obligation or the law expressly says so; when the time of delivery or service was a controlling motive for the contract; and when demand would be useless.

Why does the date of demand matter?

Delay can make the debtor liable for damages and interest. In Verga v. Harbor Star Shipping Services (2024), the Supreme Court counted compensatory interest from the extrajudicial demand, citing Article 1169 and Lara's Gifts v. Midtown.

What if both parties have obligations to each other?

Article 1169 says that in reciprocal obligations, neither party is in delay if the other does not comply or is not ready to comply properly. Once one party fulfills his obligation, the delay of the other begins.

Does a demand letter also stop the prescriptive period?

A written extrajudicial demand by the creditor interrupts prescription under Article 1155. That is a separate rule from Article 1169.

General information, not legal advice. For your case, ask a lawyer, the Public Attorney's Office (PAO) or the agency.

Share this page

Was this page helpful?

Report outdated or incorrect info

Do not include personal details such as your name, ID numbers or passwords.